Huntsman Completes Turnaround and Inspection of PO/MTBE Facility

https://www.chemnet.com   Mar 26,2010

  Huntsman Corp. said that it has completed its turnaround and inspection of its PO/MTBE facility in Port Neches, TX. This scheduled maintenance started in January 2010 and lasted approximately two months. The financial impact on the first quarter was in line with previous guidance of $30 million - $35 million including unabsorbed fixed costs.



  On March 15, 2010 a separate unit in Port Neches, TX which provides raw materials for its Performance Products division suffered a mechanical shut down expected to last approximately two weeks. The financial impact is expected to be approximately $6 - $8 million as a result of increased raw material costs; however, Huntsman expects no disruption in its ability to provide downstream products to its customers.